Variation order is an outdated term still commonly used to describe an architect’s instruction requiring alterations, additions or omissions to the quality, quantity or design of the works.
Variations Alterations, additions or omissions in work, materials, working hours, work space, etc.
The contractor shall not make any alteration and or/ modification of the permanent works. Unless and until the engineer instructs or approves a variation.
A change order is work that is added to or deleted from the original scope of work of a contract, however, depending on the magnitude of the change, it may or may not alter the original contract amount and/or completion date. Variations may also be deemed to occur if the contract documents do not properly describe the works actually required.
Variations may not (without the contractors consent):
Change the fundamental nature of the works.
Omit work so that it can be carried out by another contractor.
Be instructed after practical completion.
Require the contractor to carry out work that was the subject of a prime cost sum.
A project manager then typically generates a change order that describes the new work to be done (or not done in some cases), and the price to be paid for this new work. Once this change order is submitted and approved it generally serves to alter the original contract such that the change order now becomes part of the contract.
SBD-Works (NCB) - Prepared by the FPPA (Version 1, August 2011)
a.) If for any reason, the Engineer shall find it necessary to give an order orally, he shall as soon as possible thereafter confirm the order by change order;
b.) If the Contractor shall confirm in writing an oral order given for the purpose of GCC Clause 15.2 (a) and the confirmation shall not be contradicted in writing forthwith by the Engineer, an change order shall be deemed to have been issued for the modification.
A change order for modification shall not be required for increase or decrease in the quantity of any work where such increase or decrease is the result of the quantity exceeding or being less than that stated in the bill of quantities or price schedule, as the result of valuation of works laid down in GCC Clause 63.
15.3 Except as provided by GCC Clause 15.2 prior to any change order for modification, the Engineer shall notify the Contractor of the nature and form of such modification. As soon as possible, after receiving such notice, the Contractor shall submit to the Engineer a proposal containing: -
a.) a description of the tasks, if any, to be implemented or the measures to be taken and a program for execution; and
b.) any necessary modifications to the program of implementation of tasks or to any of the Contractor's obligations under the contract; and
c.) any adjustment to the contract price in accordance with the rules as set out in this Clause.
15.4 Following the receipt of the Contractor's submission referred to in GCC Clause 15.3, the Engineer shall, after due consultation with the Public Body and, where appropriate, the Contractor, decide as soon as possible whether or not the modification shall be carried out. If the Engineer decides that the modification shall be carried out he shall issue the change order stating that the modification shall be carried out at the prices and under the conditions given in the Contractor's submission referred to in GCC Clause 15.3 or as modified by the Engineer in accordance with GCC Clause 15.5.
FIDIC 1987
Instructions for Variations 51.2
The Contractor shall not make any such variation without an instruction of the Engineer. Provided that no instruction shall be required for increase or decrease in the quantity of any work where such increase or decrease is not the result of an instruction given under this Clause, but is the result of the quantities exceeding or being less than those stated in the Bill of Quantities.
New Engineering contract (NEC)3 Engineering and construction contract 2nd edition
A6.3.1.20 The ECC explains that “Variations to the works are made by a Project Manager’s instruction to change the Works Information…A variation may comprise deletion or addition of work or alteration to work. It may include changes to the Employer’s design, to design criteria or to performance requirements for the Contractor’s design. Issue of a revised drawing or specification is a compensation event.”
Prepare Change orders using the guidelines when contract revisions, additions, or deletions to the work are necessary. Prepare Change may be required due to: -
An error or omission in the contract
Differing site conditions
Adding a specification
Adding new items of work
Resolving a dispute
Changing the sequence of work or
Other contract changes.
Submit change orders requiring a design exception to either the appropriate design division or Field Coordination Section for approval. Ensure that any change orders meeting either of the following conditions are signed and sealed by a licensed professional engineer: -
Send all change orders with original signatures to the Construction Division, Labor and Contract Administration Branch. Approved change orders must be maintained in the original contract file located at the construction division.
Show all information and quantities about the proposed change on the change order. A performance bond is not required if the change order increases the contract cost.
For change orders requiring administrative approval, include a completed copy of the checklist with the transmittal letter of the construction division package forwarded to labor and contract administration to expedite the change order approval process.
If an agreement is not reached with the contractor regarding the scope of work and basis of payment for the change order, indicate on the change order form whether the work will proceed under force account or interim adjustment to the contract.